Mozambique LNG – onshore LNG facilities
Afungi site, Cabo Delgado, northern Mozambique
Rotational
Experience
Minimum 10 years in piping and vessel construction on Oil & Gas industrial plants
Languages
English required; Portuguese or French is an advantage
About the project
Mozambique LNG is a large-scale liquefied natural gas development. The onshore facilities comprise two LNG trains, LNG and condensate storage, marine facilities (jetty and loading), utilities and the supporting site infrastructure. Construction is delivered by an EPC Contractor and its subcontractors, in a multinational project environment.
The role
As part of the project owner's site team, the Piping, Valve & Vessel Supervisor oversees the EPC Contractor's piping, valve and vessel construction works within an assigned area. The Supervisor makes sure the works are carried out safely and in line with project requirements and specifications for construction methods, quality and schedule, up to sub-system handover to the Commissioning team. The position reports to the Field Engineering & Supervision Manager and works closely with the Package Superintendents.
Key responsibilities
Minimum 10 years of hands-on experience in piping and vessel construction on Oil & Gas industrial plants, in a supervision role.
Large-project track record
Experience on a project of comparable size and complexity (LNG, gas processing, refining or petrochemical), ideally supervising an EPC Contractor on behalf of the project owner.
Codes, standards and specifications
Working knowledge of the piping, valve and pressure vessel codes applied on such plants (e.g. ASME B31.3 Process Piping, ASME BPVC Section VIII) and the ability to check site works against project specifications and drawings (P&IDs, isometrics).
Piping erection supervision
Supervision of spool erection, supports, alignment and bolted flange joints, including stainless steel and low-temperature/cryogenic service as found on LNG trains.
Valve and vessel installation
Supervision of valve handling, preservation and installation, and of the setting of vessels, columns and exchangers, including internals installation and inspection before closure.
Quality surveillance and ITPs
Inspection of the works against approved ITPs (witness and hold points), follow-up of welding and NDT with QA/QC, and oversight of pressure testing and reinstatement.
Mechanical completion and handover
Experience taking piping systems from test packs through punch listing and close-out to sub-system handover to Commissioning.
Progress verification and planning
Ability to verify the Contractor's reported progress on the ground, take part in construction planning meetings and flag issues before they affect schedule or cost.
Method statements and technical issue resolution
Ability to contribute to and review execution plans and method statements (e.g. vessel lifting and setting, pressure testing) and to support the Superintendent in resolving technical issues; contribution to lessons learnt
HSE leadership in the field
Demonstrated safety leadership through daily site presence, with command of the high-risk activities of the discipline: lifting, work at height, confined space entry, hot work and pressure testing; immediate reporting of incidents and risks.
Afungi site, Cabo Delgado, northern Mozambique
Rotational
Experience
Minimum 10 years in piping and vessel construction on Oil & Gas industrial plants
Languages
English required; Portuguese or French is an advantage
About the project
Mozambique LNG is a large-scale liquefied natural gas development. The onshore facilities comprise two LNG trains, LNG and condensate storage, marine facilities (jetty and loading), utilities and the supporting site infrastructure. Construction is delivered by an EPC Contractor and its subcontractors, in a multinational project environment.
The role
As part of the project owner's site team, the Piping, Valve & Vessel Supervisor oversees the EPC Contractor's piping, valve and vessel construction works within an assigned area. The Supervisor makes sure the works are carried out safely and in line with project requirements and specifications for construction methods, quality and schedule, up to sub-system handover to the Commissioning team. The position reports to the Field Engineering & Supervision Manager and works closely with the Package Superintendents.
Key responsibilities
- Lead by example on safety and promote HSE commitment across Company, Contractor and Subcontractor teams; ensure compliance with all applicable HSE requirements.
- Maintain a strong physical presence on site, providing technical oversight and immediately reporting technical or coordination issues, potential risks and any HSE incident.
- Prepare, coordinate and monitor piping, valve and vessel construction activities in line with project requirements and construction procedures, up to sub-system handover to Commissioning.
- Ensure site works are properly managed and executed by the Contractor and its approved Subcontractors in accordance with the contract.
- Take part in quality surveillance programmes and inspect the works as directed in the approved Inspection and Test Plans (ITPs).
- Verify the Contractor's progress reporting for the discipline.
- Support the development of execution plans, method statements and related procedures.
- Support the discipline Superintendent in resolving technical issues, providing inputs and coordination.
- Attend construction planning meetings and anticipate technical issues before they affect schedule or cost.
- Help collect and validate lessons learnt and provide feedback to the project team.
- Degree, diploma or equivalent qualification in a related discipline and/or Oil & Gas construction.
- At least 10 years of practical experience in piping and vessel works on Oil & Gas industrial plants, with good knowledge of the relevant specifications, technical codes and standards.
- Solid knowledge of project execution best practices, gained on projects of similar size.
- Clear understanding of what drives success on large, complex projects: safety, environment, work organisation, cost, schedule and quality.
- Strong HSE culture and safety leadership, with the ability to influence critical decisions.
- Analytical, rigorous and results-oriented, able to adapt to changing constraints.
- Good interpersonal and communication skills in an international environment.
- Strong written and spoken English; Portuguese or French is an advantage.
Minimum 10 years of hands-on experience in piping and vessel construction on Oil & Gas industrial plants, in a supervision role.
Large-project track record
Experience on a project of comparable size and complexity (LNG, gas processing, refining or petrochemical), ideally supervising an EPC Contractor on behalf of the project owner.
Codes, standards and specifications
Working knowledge of the piping, valve and pressure vessel codes applied on such plants (e.g. ASME B31.3 Process Piping, ASME BPVC Section VIII) and the ability to check site works against project specifications and drawings (P&IDs, isometrics).
Piping erection supervision
Supervision of spool erection, supports, alignment and bolted flange joints, including stainless steel and low-temperature/cryogenic service as found on LNG trains.
Valve and vessel installation
Supervision of valve handling, preservation and installation, and of the setting of vessels, columns and exchangers, including internals installation and inspection before closure.
Quality surveillance and ITPs
Inspection of the works against approved ITPs (witness and hold points), follow-up of welding and NDT with QA/QC, and oversight of pressure testing and reinstatement.
Mechanical completion and handover
Experience taking piping systems from test packs through punch listing and close-out to sub-system handover to Commissioning.
Progress verification and planning
Ability to verify the Contractor's reported progress on the ground, take part in construction planning meetings and flag issues before they affect schedule or cost.
Method statements and technical issue resolution
Ability to contribute to and review execution plans and method statements (e.g. vessel lifting and setting, pressure testing) and to support the Superintendent in resolving technical issues; contribution to lessons learnt
HSE leadership in the field
Demonstrated safety leadership through daily site presence, with command of the high-risk activities of the discipline: lifting, work at height, confined space entry, hot work and pressure testing; immediate reporting of incidents and risks.